For two decades, technical communicators have turned to TechWhirl to ask and answer questions about the always-changing world of technical communications, such as tools, skills, career paths, methodologies, and emerging industries. The TechWhirl Archives and magazine, created for, by and about technical writers, offer a wealth of knowledge to everyone with an interest in any aspect of technical communications.
Subject:How long does it take you? From:Wolf Lahti <wduby -at- PACCAR -dot- COM> Date:Tue, 9 Jan 1996 10:30:03 -0800
Tracy Boyington said
>How do you estimate how long it will take to complete a project? What
>criteria do you use? What are your benchmarks?
I've always been terrible at estimating time to complete a project or any
portion of one. Fortunately this hasn't been a problem because I'm
apparently speedier than average. Former managers have given me assignments
that they estimate would take, for instance, three days to a week, and I've
typically had it done for them in a matter of hours.
However nice this may be, it does not contribute to a good sense of task
estimating.
---------------------------------