For two decades, technical communicators have turned to TechWhirl to ask and answer questions about the always-changing world of technical communications, such as tools, skills, career paths, methodologies, and emerging industries. The TechWhirl Archives and magazine, created for, by and about technical writers, offer a wealth of knowledge to everyone with an interest in any aspect of technical communications.
> To produce a more precise estimate for any given project, adjust your metric
> up or down based on your assessment of any special factors for that project.
> Build your own formula; what works for me is a formula I made with the
> following factors: writer ability (in your case, it's just you!), system
> size, system availability and stability, quality and availability of specs,
> SME availability and quality, and whether it's a rush job. I use scales of
> 1-10 for each. (I have slightly different formulas for training and for
> help.)
>
>
> Some estimates will turn out to be a little off. So you need to look back at
> the end of each project and figure out why. In some cases, your formula was
> correct, just the data wasn't. For example, say your actual page count
> turned out higher or lower than your initial outline suggested. That's okay.
> To keep automatically refining your formula, keep modifying your hours/page
> metric based on the actual results from each project you do. Your estimates
> should quickly become more and more accurate with this recursive formula.
<snip>
> It's absolutely crucial, at least for me, to do it this way if I want to be
> accurate. If I just used a thumb-in-the-air kind of method, I would
> chronically underestimate. I guess I just want to please or something. By
> forcing myself to go through the details, I eliminate that tendency for
> error.
>
After you are finished, take the contingency factor most beneficial to
you and double it.
--
Peter
Mailto:peternew -at- optonline -dot- net
Adapting old programs to fit new machines
usually means adapting new machines to
behave like old ones.
*** Deva(tm) Tools for Dreamweaver and Deva(tm) Search ***
Build Contents, Indexes, and Search for Web Sites and Help Systems
Available now at http://www.devahelp.com or info -at- devahelp -dot- com
Sponsored by Cub Lea, specialist in low-cost outsourced development
and documentation. Overload and time-sensitive jobs at exceptional
rates. Unique free gifts for all visitors to http://www.cublea.com
---
You are currently subscribed to techwr-l as: archive -at- raycomm -dot- com
To unsubscribe send a blank email to leave-techwr-l-obscured -at- lists -dot- raycomm -dot- com
Send administrative questions to ejray -at- raycomm -dot- com -dot- Visit http://www.raycomm.com/techwhirl/ for more resources and info.